Stream flows and flow duration curves at Watana, Devil Canyon, Gold Creek, Sunshine and Susitna Station for Watana and Devil Canyon in 2002 and 2020 : report
by
 
HARZA-EBASCO Susitna Joint Venture.

Title
Stream flows and flow duration curves at Watana, Devil Canyon, Gold Creek, Sunshine and Susitna Station for Watana and Devil Canyon in 2002 and 2020 : report

by Harza-Ebasco Susitna Joint Venture ; prepared for Alaska Power Authority.

Publication Information
[Anchorage, Alaska] : Alaska Power Authority, [1985]

Physical Description
566 p. in various pagings : ill. ; 28 cm.

Series
Document ; no. 2603

General Note
Chiefly tables and graphs.
 
At head of title: Susitna Hydroelectric Project.
 
"February 1985."
 
"Susitna File No. 6.18.7.5."
 
"Volume 4, appendix F."
 
Volume 4 (appendix F) is part of a multi-volume set of seven reports differently titled and numbered 2600-2606 in the Document series.
 
"Federal Energy Regulatory Commission project no. 7114"--Cover.

Corporate Subject
Susitna Hydroelectric Project -- Environmental aspects.

Subject Term
Streamflow -- Alaska -- Susitna River.
 
Stream measurements -- Alaska -- Susitna River.

Added Corporate Author
HARZA-EBASCO Susitna Joint Venture.

Type of Report
Final report.

Citation Reference Notes
Assigned APA document no. 2603 in Susitna Hydroelectric Project document index.

Additional Physical Form Available
Available also in microfiche format and electronic format on the Internet.

Variant Title
Susitna Hydroelectric Project. Stream flows and flow duration curves at Watana, Devil Canyon, Gold Creek, Sunshine and Susitna Station for Watana and Devil Canyon in 2002 and 2020 : report
 
Cover title: Stream flows and flow duration curves at Watana, Devil Canyon, Gold Creek, Sunshine and Susitna Station for Watana and Devil Canyon operation in 2002 and 2020
 
Added title page title: Appendix F, Susitna Hydroelectric Project, Stream flows and flow duration curves at Watana, Devil Canyon, Gold Creek, Sunshine and Susitna Station for Watana and Devil Canyon in 2002 and 2020
 
Caption title: Case E-VI alternative flow requirements, Appendix F, Weekly flow duration curves for the Susitna River basin 2002 and 2020 energy demands


LibraryCall NumberTypeStatus
ARLISTK1425.S8F472 no.2603BookGeneral Collection
ARLISTK1425.S8F472 no.2603BookGeneral Collection
ARLISM/Fiche TK1425.S8F472 no.2603MicroformMedia
Electronic ResourcesONLINEONLINE-ARLInternet